As of 9/3/2015, the following is done and pending:

Exterior Renovations

1. All large windows removed

2. New end wall siding installed & stained

3. Opening for gable end fan roughed-in

4. Pending: Replace exterior door frames, doors and door hardware

5. Pending: Install & power exhaust fan

6. Pending: Paint newly replaced doors

Interior Work

1. Memorabilia & plaques removed to storage

2. New electrical receptacles and lighting installed

3. Side & end walls insulated

4. New paneling & trim on side and end walls

5. New paneling & trim painted

6. Pending: New HVAC ductwork above ceiling

7. Pending: New insulated ceiling panels

8. Pending: Purchase and install ceiling fans

9. Pending: Convert one restroom to HVAC room

10. Pending: Install refurbished HVAC unit with power, gas & piping

11. Pending: Purchase and install new projection screen

12. Pending: Reinstall memorabilia

Ron Rosenberry works tirelessly on the Ware Dining Hall paneling.

Ron Rosenberry works tirelessly on the Ware Dining Hall paneling.

Insulation can be seen as the paneling is cut for the Ware Dining Hall walls.

Insulation can be seen as the paneling is cut for the Ware Dining Hall walls.

The panels are installed on the Ware Dining Hall walls.

The panels are installed on the Ware Dining Hall walls.

The Octoraro 22 carpentry crew works to frame in the end of the Ware Dining Hall.

The Octoraro 22 carpentry crew works to frame in the end of the Ware Dining Hall.

Share this:

Categories: Uncategorized

WP2Social Auto Publish Powered By : XYZScripts.com